Two smaller dams show “improvement”

Michael Hawthorne

Dam levels taken at 07:00 this morning at the Newton Reservoir in Kimberley show a slight improvement to the two smaller dams.

DA Councilor Ockert Fourie says the early shutdown yesterday has improved levels to the 2 smaller dams, but the levels of the others are still critically low.

102ML at 9ft 3″
91ML at 10ft
45ML at 15ft 4″
23ML at 15ft 6″

Previous dam levels on Saturday morning

102ML at 9ft 3″
91ML at 10ft
45ML at 12ft 4″
23ML at 13ft 6″

Repairs planned on 600mm and 350mm

Fourie says a contractor is currently busy surveying major leaks by means of a drone to pinpoint the location of all the major leaks.

He says repairs to the 350mm pipeline next to the fly-overs on the N8 will be carried out tomorrow, followed by repairs to the 600mm pipeline behind Roodepan.

All information regarding shutdowns, repairs and progress will be communicated, Fourie concludes.